Environmental Projects
 
 
 
 
 
 

DPW Projects– Environmental Management Division






Town Brook Dam Removal

TownBrookweb.jpgTownBrook4.jpg

Scope: The Town of Plymouth Department of Public Works Environmental Management Division is completing design and entering the permitting phase for the Off Billington Street and Plymco Dams located on Town Brook.

This Feasibility study (below) assessed the current conditions of the structures, public safety, environmental and cost issues associated with repairing or removing these structures. It includes survey, HEC-RAS modeling, flow and flood analysis, fish passage analysis and sediment contamination review. It provides cost estimates with each alternative to the Town for final decision-making.

Partners:  Town of Plymouth Planning Department, NOAA Restoration Center, Massachusetts Riverways Program, Massachusetts Division of Marine Fisheries, United States Fish and Wildlife Service, Massachusetts Bays Program.

Status: Feasability study completed.  Awaiting grant funding for the final design for the dam removal.

Schedule/Funding: Feasibility study completed Winter 2007.  Currently working on Final Design and Permitting

Funding Sources:
                        $50,000 CLF/NOAA
                        $14,445 CLF/NOAA
                        $35,000 CLF/NOAA
                        $50,000 Gulf of Maine Council
                        $50,000 American Rivers
                        $50,000 CWRP
                        $30,000 Riverways Program
                        $25,000 Riverways Program
                        $54,000 CLF/NOAA
                        $8,000  USGS Sampling & Labwork
                        $20,000.00      Town of Plymouth
                        

Reports & Presentations: (click to download) if you have any problems downloading please contact kmichaelis@townhall.plymouth.ma.us









Eel River Headwaters Restoration Project

Headwatersweb0.jpgHeadwaters1.jpgHeadwaters2.jpg

Scope: The Town of Plymouth Department of Public Works Environmental Management Division is working with project partners in the restoration of approximately 40 acres of wetlands and 1.25 miles of the Eel River channel originating at the headwaters.  The channelized stream will be restored to a natural sinous channel with riparian wetlands through the removal of the water control structures, re-grading of the bogs and the planting of new wetland resource areas, including Atlantic white cedar (click here for pictures).  The final design plans are expected in the winter of 2007 for the wetland and river channel restoration for bogs 1-7.  The final design for the potential removal of the Sawmill Pond Dam located downstream is awaiting funding.  

This project will provide potential new habitat for brook trout and significant reductions in nutrient loading downstream in the Eel River as well as restoring natural wetland functions and values on a large scale.

Hayden Pond Land Acquisition
As an expanded project scope, the Town reviewed potential land along the Eel River to preserve as conservation land.  The Town has acquired a 13 acre parcel along Hayden Pond with $38,500 of the USFWS National Coastal Wetlands Conservation Grant (listed below) and $91,500 of Challenge Grant Money.  
Photographs of Hayden Pond Parcel Acquisition

HaydenLand3.jpg
HaydenLand2.jpg
HaydenLand1.jpg


Project Partners: Natural Resources Conservation Service, Massachusetts Riverways, United States Fish and Wildlife Service, Massachusetts Coastal Zone Management, Massachusetts Bays Program, The Nature Conservancy, Eel River Watershed Association.

Conceptual & 99% Design Report & Plans:

Status:
Phase I assessment, survey, data collection and conceptual design completed.  
Final Design for the Wetland & River Restoration completed.
Currently working on the permitting phase of the project and the completion of the Final Design for the Sawmill Pond Dam Removal.  

Permitting:
MA Department of Fish & Game has submitted and updated Application for 401 Water Quality Certification to include the entire project for the Town of Plymouth.  
Click on link to access the application.  Public Comment period ends February 18, 2009.

The Town has submitted the Notice of Intent (28MB) in reference to the Massachusetts Wetlands Protection Act.  The Conservation Commission Public Hearing will be held Monday, March 16th at 8:15pm Town Hall.  

Funding Sources:


Source
Year
Amount
NRCS
350,800
Riverways Program
FY2006
30,000
Town of Plymouth
FY2006
25,258
Town of Plymouth
FY2007
26,761
Town of Plymouth
FY2008
3,065
Riverways Program
FY2007
49,333
Riverways Program
FY2007
4,995
Riverways Program
FY2008
10,667
MCZM
FY2007
20,000
USFWS
FY2007
4,995
DEP Mitigation Fund
180,000
DEP 319 Grant
Awarded
400,000
National Coastal Wetlands Conservation
Awarded
1,000,000
CZM WRP
Awarded
50,000
Riverways Program
FY2008
15,000
Riverways Program
FY2008
5,000
AD Makepeace Grant
Awarded
5,000
Town of Plymouth IMP
FY09
8,000
Town of Plymouth
FY09
110
Total
2,188,984




Pond Monitoring Program
Approved at Spring Town Meeting 2008

The Pond Monitoring Program was created to develop a baseline and assess water quality on a number of ponds in Plymouth. To date, four pond associations and 10 ponds are currently monitored.  There are two portions of the monitoring program.  The first includes the Biological Monitoring which is conducted by a professional biologist/limnologist.  The second includes the Nutrient Monitoring which is conducted by each of the Associations.  

Biological Monitoring  - Water column profiles, secchi transparency, photoplankton sampling, macrophyte scouting, bathymetric data

Halfway Pond, Round Pond, Gallows Pond, Bloody Pond, Little Long Pond, Long Pond, Billington Sea, Little Pond, Great Herring Pond, Great South Pond

Nutrient Monitoring & Sampling - Collect water quality data, generate solutions & implementation strategies to improve water quality

Six Ponds Association Monitors:  Halfway Pond, Round Pond, Gallows Pond, Bloody Pond, Little Long Pond, Long Pond,
Billington Sea Association Monitors:  Billington Sea
Great Herring Pond Association Monitors: Great Herring Pond
Twin Lakes Association Monitors:  Ezekial Pond, White Island Pond







Harbor Dredging

Scope: The Town of Plymouth Department of Public Works Environmental Management Division is working assessment, engineering and permitting to dredge portions of Plymouth Harbor. The harbor has not been dredged in decades resulting in safety concerns and loss of mooring areas.

This project will provide for improved navigation in the harbor, increased mooring areas and the long term use of the harbor for commercial and recreational boats.

Partners:  Town of Plymouth Harbormasters Office, Massachusetts Seaport Council, Massachusetts Division of Conservation and Recreation – Office of Waterways.

Status: Engineering and permitting are on-going. Phase 1 sediment testing is complete.

Schedule/Funding:
Phase I:  Fall 2007
Funding Sources:
                        $160,000.00             Massachusetts Seaport Council





Engineering for new T-Wharf

Scope: The Town of Plymouth Department of Public Works Environmental Management Division is working on engineering and permitting a new T-Wharf for Plymouth Harbor.

This project will provide engineering and permitting services for a new T-Wharf to serve the commercial fishing fleet in Plymouth Harbor. The new wharf will provide for loading and unloading of vessels, vehicular access, jib cranes, utilities and storm protection.

Partners:  Town of Plymouth Harbormasters Office, Massachusetts Seaport Council, Massachusetts Division of Conservation and Recreation – Office of Waterways.

Status: Permitting is ongoing.

Schedule/Funding:
Engineering and Permitting: Permitting is ongoing
Funding Sources:
                        $150,000.00             Massachusetts Seaport Council

T-Wharf1.jpgT-Wharf2.jpeg