Paving Operations - Sandwich Street, Nook Road, and North Street

The Town of Plymouth’s Department of Public Works (“DPW”) seeks to notify residents and visitors that, starting on Monday, June 7, 2021, paving contractor Rochester Bituminous will begin roadway milling and leveling operations in preparation for the pavement of Sandwich Street, Nook Road, and North Street.

Barring inclement weather and unforeseen circumstances, work is expected to take place on weekdays between the hours of 7:00 a.m. to 5:00 p.m., in accordance with the following schedule:

Sandwich Street, from Lollipop Lane to Warren Avenue

  • Monday, June 7th – Milling of Roadway Surface
  • Tuesday, June 8th – Milling of Roadway Surface, Continued
  • Thursday, June 10th – Application of Leveling Course
  • Friday, June 11th – Application of Leveling Course, Continued

Nook Road

  • Tuesday , June  8th – Milling of Roadway Surface
  • Friday, June 11th – Application of Leveling Course

North Street

  • Monday, June 7th – Milling of Roadway Surface
  • Thursday, June 10th – Application of Leveling Course

Please Note: The final paving dates for Sandwich Street, Nook Road, and North Street will be scheduled, following necessary sidewalk repairs planned for all three roadways.  The Town will issue an updated press release on the schedule for the final pavement of these roads.

The DPW will deploy message boards to alert motorists of the forthcoming work. During the scheduled work, the DPW and the contractor will make every effort to keep traffic flowing in both directions, but detours may be required.   In such instances, the DPW will work with the contractor and the Plymouth Police Department’s detail officers on the placement of barrels and detour signage, to keep traffic flowing as smoothly as possible.  The public is advised to drive with caution and plan for traffic delays and temporary access restrictions.  

The Town appreciates the community’s patience during these important roadway improvement projects.General questions may be directed to the DPW’s Highway Division at (508) 830-4162, ext. 12101, during the DPW Office’s normal business hours, 7:30 a.m. to 3:30 p.m.