The sewer force main rehabilitation project on Sandwich Street, began in March of 2024 and was completed in April of 2024.
The project involved cured in place (CIPP) lining inside the existing sewer force main on Sandwich Street between Winter Street and Nook Road. Construction also included excavation of access pits along the existing force main and installation of a temporary bypass sewer pipe.
Insituform Technologies of Chesterfield, Missouri completed the work as the Town’s contractor.